The reporting clock does not wait for the perfect PowerPoint.

·

Cyber incidents create a peculiar management challenge.

The facts arrive slowly. The deadlines do not.

The Commission incident illustrates why boards need to distinguish three separate timelines: technical detection, legal awareness, and public communication.

IT-Connect reports that the attack was reportedly detected on 22 October, that ARTEX-related activity was identified in early November, and that public confirmation followed the reporting on 19 November. Those reported dates do not, by themselves, establish when a particular legal notification obligation started—or whether it was met.

That distinction matters.

Otherwise, a board discussion quickly becomes a legal conclusion assembled from newspaper timestamps.

For significant incidents, Regulation (EU) 2023/2841 requires EU entities to send CERT-EU an early warning without undue delay and within 24 hours of awareness. An incident notification follows without undue delay and within 72 hours. A final report is generally due within one month of that notification; ongoing incidents follow a progress-report and subsequent final-report mechanism.

Separate personal-data-breach obligations can arise under Regulation (EU) 2018/1725, with their own trigger, recipient and assessment.

One incident. Different obligations. Different clocks.

An excellent environment for discovering that everybody thought Legal was handling it.

For the Commission, the challenge is to reconstruct a defensible chronology: what was known, by whom, when significance was assessed, what was reported, and how the information developed.

For your board, the challenge is to ensure that chronology can be produced without an archaeological expedition through executive inboxes.

Ask management to demonstrate four things.

  1. One: a notification matrix that identifies applicable obligations, decision owners, recipients and deputies.
  2. Two: clear escalation criteria for nights, weekends and unavailable executives.
  3. Three: a decision log that distinguishes confirmed facts, working assumptions and unresolved questions.
  4. Four: a process for phased updates rather than waiting for complete certainty.

Early reporting is not the same as publishing an unverified theory. An organisation can acknowledge an incident, explain what remains unknown and update the relevant authority as evidence develops.

The board should not become an emergency editorial committee approving every sentence. It should ensure the operating model allows authorised people to act on time.

For the Commission, a polished public explanation cannot substitute for evidence that the right recipients received the right information when required.

For your organisation, the test is straightforward:

“Can we show who would make a notification decision at 02:00 on Sunday?”

A shared mailbox is not a succession plan.